Progress - Day 54

Progress over the last ten days has felt slow even though we checked two big items off the list.

On Wednesday of last week the spray foam crew began insulating. It took them almost four days to complete the entire house, twice as long as they had originally estimated, and were delayed a further two days after completely running out of foam on the second day. They didn't finish the final touch-ups until this Wednesday.

In between visits from the spray foam crew, the new furnace and ductwork got installed last weekend.

This next week will be spent finishing off the mile long list of little things that need to be done before drywall can go up. Phone lines, internet lines, tv cables, stereo wire, vacuum lines, backing, vapour barrier, sound batt...